- Permitted capacity
- 150 kt/a
- Commissioned
- 2007
- Energy recovery
- CHP
Discover technical data and facts about the Waste-to-Energy and the sewage sludge mono incineration plant in Stavenhagen.
| Thermal input | 49.5 MWth |
|---|---|
| Feedstock | Refuse-derived fuel |
| Electricity generated | WtE Monitor+Available with WtE Monitor+ |
| District heat use | WtE Monitor+Available with WtE Monitor+ |
| Process steam delivered | WtE Monitor+Available with WtE Monitor+ |
| Operating hours | 8,000 h/a |
| Ownership | WtE Monitor+Available with WtE Monitor+ |
| Modernisation / expansion | WtE Monitor+Available with WtE Monitor+ |
| Projects in progress | Sewage sludge mono-incineration plant commissioned 2024 supplying waste heat for district heating |