Waste-to-energy plant ·

Tilbury

Viridor Tilbury
Source: Viridor

Operator: Viridor · Under construction · Data verified 22.10.2026

Permitted capacity
379.7 kt/a
Incineration lines
1
Commissioned
2028
Energy recovery
Electricity

Viridor is building the Thameside Energy Recovery Facility on the former Cargill sweeteners site on the north-west side of Tilbury Docks in Thurrock, Essex, next to the Tilbury Green Power biomass plant.

Viridor bought the development rights for the consented ‘Tilbury Docks Phase 2’ project from the Irish utility ESB in September 2022, had the environmental permit varied in January 2024 to a single-line inclined moving-grate plant for 379,658 tonnes per year (43.3 t/h, 126.4 MW thermal, up to 44 MW electrical) and reached financial close in November 2024.

Kanadevia Inova is building the plant under a turnkey EPC contract over about 42 months. By 2026 the waste bunker, stack and main concrete structure will be complete and commercial operation is targeted for 2028. The plant is designed CHP-ready with steam and hot-water pass-outs, and carbon capture is considered a possible future option.

Technical data
Firing systemGrate
Firing system details WtE Monitor+Available with WtE Monitor+
Thermal input126.4 MWth
Hourly capacity WtE Monitor+Available with WtE Monitor+
Feedstockresidual municipal solid waste, commercial and industrial waste, refuse-derived fuel
Accepted waste types (EWC codes) WtE Monitor+Available with WtE Monitor+
Electrical output WtE Monitor+Available with WtE Monitor+
Flue gas cleaning WtE Monitor+Available with WtE Monitor+
Technology suppliers WtE Monitor+Available with WtE Monitor+
Designer / EPC contractor WtE Monitor+Available with WtE Monitor+
Ownership WtE Monitor+Available with WtE Monitor+
Commissioning by line2014 (original permit for 170,000 t/a SRF/wood plant, Tilbury Green Power Phase 2); September 2022 (Viridor acquires development rights from ESB); January 2024 (permit variation EPR/WP3007LM/V002 to 379,658 t/a); November 2024 (financial close, EPC contract with Kanadevia Inova, start of construction); 2028 (planned commercial operation)
Projects in progressUnder construction since November 2024 (42-month build and commissioning programme): waste bunker complete, stack erected, main concrete structure largely finished, M&E works and steel erection in 2026; CHP-ready design with steam/hot-water pass-outs, CHP options to be considered during construction; carbon capture and storage named as a possible future opportunity; commercial operation targeted for 2028
AddressThameside Energy Recovery Facility, former Cargill Sweeteners site, Tilbury Dock, Tilbury RM18 7NU

Coverage of this plant

Location

Nearby plants

Sources

9 sources for this profile. The list is part of WtE Monitor+

AI search

Ask WtE Monitor

Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.

Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy

3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+