Waste-to-energy plant ·

Rivenhall

Rivenhall Waste-to-Energy-Plant
default

Operator: Indaver · Operating · Data verified 22.10.2026

Permitted capacity
595 kt/a
Incineration lines
2
Commissioned
2026
Energy recovery
Electricity

The Rivenhall Integrated Waste Management Facility near Kelvedon in Essex is operated by Indaver Rivenhall Limited, a subsidiary of the Belgian Indaver group, and is Indaver’s largest energy-from-waste plant.

The two-line moving-grate plant was designed and built by Kanadevia Inova in a former quarry on the old Rivenhall airfield. Construction began in October 2022, first waste was accepted in July 2025, provisional acceptance was issued on 18 April 2026 and the plant was officially opened on 18 June 2026.

It is permitted for up to 595,000 tonnes of residual municipal and commercial waste a year and generates around 55 MW of electricity, with Essex County Council as anchor customer under a residual waste contract that started in April 2025. Further consented phases of the site (MBT, MRF, anaerobic digestion, paper pulp plant) and the supply of heat and CO2 to planned adjacent greenhouses are still to follow.

Technical data
Firing systemGrate
Firing system details WtE Monitor+Available with WtE Monitor+
Waste calorific value WtE Monitor+Available with WtE Monitor+
Feedstockresidual municipal solid waste, commercial and industrial waste
Steam parameters WtE Monitor+Available with WtE Monitor+
Electrical output WtE Monitor+Available with WtE Monitor+
Flue gas cleaning WtE Monitor+Available with WtE Monitor+
Technology suppliers WtE Monitor+Available with WtE Monitor+
Designer / EPC contractor WtE Monitor+Available with WtE Monitor+
Ownership WtE Monitor+Available with WtE Monitor+
Commissioning by line2025 (first waste 21 July 2025, hot commissioning from August 2025, Lines 1–2); 2026 (provisional acceptance certificate 18 April 2026; official opening 18 June 2026)
Projects in progressPhased build-out of the consented Integrated Waste Management Facility (MBT 170,000 t/a, MRF 300,000 t/a, anaerobic digestion 30,000 t/a, paper pulp plant 170,000 t/a) still outstanding; Development Consent Order granted December 2024 to raise generating capacity to up to 65 MW; planning applications submitted April 2025 for phased delivery and space for a future carbon capture plant (objected to by Braintree District Council); supply of heat, electricity and CO2 to planned adjacent glasshouses (planning permission secured, long-term target 30,000 t of tomatoes a year); long-term service agreement with Kanadevia Inova (June 2025)
AddressRivenhall Airfield, Woodhouse Lane, Kelvedon, Essex CO5 9DF

Coverage of this plant

Location

Nearby plants

Sources

12 sources for this profile. The list is part of WtE Monitor+

AI search

Ask WtE Monitor

Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.

Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy

3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+