Operator: Zweckverband Kehrichtverwertung Zürcher Oberland (KEZO) · Operating · Data verified 08.10.2026

Permitted capacity
200 kt/a
Incineration lines
3
Commissioned
1976
Energy recovery
CHP

The KEZO (Kehrichtverwertungsanlage Zürcher Oberland) in Hinwil is one of Switzerland’s largest and most technologically advanced waste-to-energy plants, operated by the Zweckverband KEZO.

With three incineration lines processing waste from the Zürich Oberland and beyond, the facility delivers significant electricity to the national grid and exports thermal energy to district heating customers. KEZO is also notable for being the host site of the world’s first commercial direct air capture plant (Climeworks), powered by the residual heat of the incineration process.

Technical data
Firing systemGrate
Hourly capacity WtE Monitor+Available with WtE Monitor+
Waste calorific value WtE Monitor+Available with WtE Monitor+
Feedstockmunicipal solid waste, commercial and industrial waste
Accepted waste types (EWC codes) WtE Monitor+Available with WtE Monitor+
Electricity generated WtE Monitor+Available with WtE Monitor+
Heat delivered WtE Monitor+Available with WtE Monitor+
District heat use WtE Monitor+Available with WtE Monitor+
Flue gas cleaning WtE Monitor+Available with WtE Monitor+
Technology suppliers WtE Monitor+Available with WtE Monitor+
Ownership WtE Monitor+Available with WtE Monitor+
Commissioning by line1976 (two lines); 1995/1996 (one line, replacing the original Line 1 from 1970)
Modernisation / expansion WtE Monitor+Available with WtE Monitor+
Projects in progressClimeworks direct air capture plant on the KEZO roof using waste heat (2017); KEZO/Sulzer CO2 capture pilot from flue gas, up to 1,000 t CO2/a (announced July 2025); replacement plant with one line and approx. 120,000 t/a, approx. CHF 350 million, commissioning planned 2031 (earlier 2H 2030), with district heat output planned to rise to approx. 225 GWh/a and a later CO2 capture stage of up to 120,000 t/a; site masterplan to 2045
AddressWildbachstrasse 2, 8340 Hinwil

Coverage of this plant

Location

Nearby plants

Sources

11 sources for this profile. The list is part of WtE Monitor+

AI search

Ask WtE Monitor

Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.

Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy

3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+