InBW Tenders Commercial Waste Capacity at Virginal WtE Plant

inBW is offering commercial waste capacity at its Virginal WtE plant – with a floor price and just seven days to bid. The plant’s recent figures show why the tonnes matter.

InBW Tenders Commercial Waste Capacity at Virginal WtE Plant
Waste containers for commercial waste (Source: Del Harper – stock.adobe.com
  • inBW tenders 5,000 t/yr of commercial waste capacity at its Virginal WtE plant, in three lots.
  • Offers are due by 1 December 2026; contracts start on 1 January 2027.
  • The minimum price is €120/t, charged as a flat capacity reservation fee.
  • Contracts run for at least four years; longer terms score better.
  • In 2025, line 2 ran at 70 per cent availability and the plant treated 97,497 t.

The Walloon Brabant intermunicipal company inBW has opened a call for offers for treatment capacity for non-hazardous commercial and industrial waste (déchets industriels banals, DIB) at its Waste-to-Energy plant in Virginal, Belgium. The notice was published on 24 November 2026. However, offers must reach inBW by 1 December 2026 at 9:00, seven days after publication. Contracts are to start, in principle, on 1 January 2027.

inBW owns and operates the plant, known as the unité de valorisation énergétique (UVE). It mainly treats household waste from the member municipalities and from Braine-le-Comte. According to inBW, the environmental permit also provides capacity for other waste types such as DIB. The tender document (reference VIR 09 2026) puts this availability at 36,000 to 40,000 tonnes per year and refers to line 2 of the plant. Moreover, inBW says the aim is to make better use of the available capacity and to secure the economic balance of the plant.

Three Lots Totalling 5,000 Tonnes

The capacity on offer is divided into three lots: two of 1,000 tonnes each and one of 3,000 tonnes, 5,000 tonnes in total. Candidates may bid for one or several lots. However, a single partner can be awarded no more than 5,000 tonnes per year.

The minimum contract term is four years. Longer terms are taken into account in the evaluation. Ordinary termination before expiry is excluded, except in cases of force majeure.

Minimum Price of 120 Euros per Tonne

Prices are to be quoted in euros per tonne, excluding VAT and taxes. inBW sets a minimum price of 120 euros. Only candidates offering at least this amount are admitted to negotiations. After that, they are invited to submit a final offer.

The price is designed as an annual flat fee for reserving capacity. It remains due if the partner delivers fewer tonnes than reserved. It also applies if inBW has to have the waste treated elsewhere. The price is fixed and cannot be revised, apart from an annual indexation provided for in the contract and changes in taxes, levies or charges applying to the operation of the plant. Moreover, payment is made in advance, monthly or quarterly.

inBW lists five award criteria in descending order of importance: the reservation price, the contract term offered beyond four years, the origin of the waste measured as transport distance to the plant in kilometres, the storage capacity of the candidate in cubic metres, and the maximum lower heating value per lot. The document gives no weighting in points or percentages. The lower heating value stated by the candidate must not exceed 15 MJ/kg. This value must be observed throughout the contract term.

Deliveries are planned by the number of semi-trailers per week, to be agreed in the contract. inBW schedules two maintenance shutdowns per year. It guarantees treatment of the reserved tonnage provided that the waste quality and the delivery schedule are respected. Of course, this applies except for force majeure. The capacity is reserved exclusively for the contracting partner and cannot be transferred without the consent of inBW.

According to the document, the procedure is neither a public contract nor a service or works concession within the meaning of the Belgian laws of 17 June 2016. Only the general principles applying to intermunicipal companies apply, in particular equal treatment and the duty to state reasons. inBW reserves the right to abandon the procedure at any time, including after a partner has been selected. Furthermore, it may leave individual lots unawarded or re-tender them. Candidates waive any compensation and bear their own costs.

Offers are to be submitted electronically by e-mail and remain valid for three months. Questions can be submitted until 26 November 2026, and inBW will answer by 27 November 2026. No information is given orally. The contacts named are Frédéric Vandamme and Mauro Russo (virginal@inbw.be). inBW may postpone the deadline.

Earlier Contracts Cover 26,000 Tonnes per Year

inBW has not published award results for earlier DIB procedures. Its official reports give aggregate volumes only. They name neither the contracting partners nor the prices.

The 2023 management report stated that contracts for 25,000 tonnes of DIB over four years were being concluded. It added that this volume would not offset the decline in residual household waste. In addition, a new procedure was to be launched at the end of 2024. In May 2024, inBW signed contracts with private operators for 26,000 tonnes of DIB per year over four years, according to the 2024 annual report.

DIB deliveries to Virginal rose from 18,067 tonnes in 2023 to 39,249 tonnes in 2024, the 2024 management report shows. The total quantity treated increased from 98,186 to 104,673 tonnes. Furthermore, inBW put the additional income from the treatment of private waste at an estimated 1,975,000 euros.

In its strategic plan for 2023 to 2025, inBW had set a target of 20,000 tonnes per year from industrial partnerships. The 2024 evaluation reported 26,000 tonnes as of September 2024. In addition, the 2025 evaluation reported 31,000 tonnes.

According to the minutes of the general assembly of 17 December 2025, the contracts cover around 80 per cent of DIB deliveries. In addition, they secure tonnage at an agreed, indexed price for three years. The minutes describe the objective as filling the capacity freed up by the decline in residual household waste with DIB.

Line 2 Limited to 70 Per Cent in 2025

The Virginal plant has a treatment capacity of 116,000 tonnes per year. In 2025 it treated 97,497 tonnes, 7.2 per cent less than in the previous year. Also, it generated 38,799 MWh of electricity, according to the 2025 annual report. inBW attributes the decline mainly to line 2, whose availability was limited to 70 per cent. Around 8,000 tonnes of waste could not be treated. Furthermore, the loss of electricity production is estimated at 5,000 MWh. Technical and economic analyses of an investment in line 2 are under way.

The 2025 management report states that invoiced tonnages fell by 8 per cent, equivalent to about 0.9 million euros in lost revenue. Lower volumes of bulky waste from the recycling centres were only partly offset by higher DIB volumes. The treatment segment, which also includes the Mont-Saint-Guibert transfer centre, closed 2025 with a deficit of 2,649,097 euros. inBW attributes half of this to the fire at the transfer centre and half to the Virginal plant.

Read More

AI search

Ask WtE Monitor

Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.

Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy

3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+


Discover more from WtE Monitor

Subscribe to get the latest posts sent to your email.

Free newsletter

Waste-to-energy news, straight to your inbox.

Projects, policy and plant data from across Europe. Get every story as it is published, or switch to a daily or weekly digest.

Free. Confirm by email. Change the frequency or unsubscribe at any time.

Leave a Reply