Waste-to-energy plant ·

Walsall

Ulm’s WtE Plant Charts Its Next Move
A long cloud of white smoke escaping from a metallic chimney against a deep blue sky.

Operator: Encyclis · Under construction · Data verified 22.10.2026

Permitted capacity
478.3 kt/a
Incineration lines
1
Commissioned
2027
Energy recovery
Electricity

Encyclis (formerly Covanta Europe) is building the Walsall Energy Recovery Facility on a brownfield site off Fryers Road in Bloxwich, on the northern edge of Walsall in the West Midlands.

The project was originally developed by BH EnergyGap as a two-line gasification scheme and was converted to a conventional single-line moving-grate plant after Encyclis took full ownership and reached financial close in December 2023. It is the first plant wholly owned by Encyclis.

Kanadevia Inova started on-site construction in November 2024 under a turnkey EPC contract. The plant is permitted for 478,300 tonnes of residual household and commercial waste per year (54.6 t/h), will generate up to 49.9 MW of electricity (43.5 MW export) and is designed CHP-ready for a planned district heat network with up to 20 MW of heat. By July 2026 the steam turbine, boiler drum and grate components had been installed, with operation expected in late 2027.

Technical data
Firing systemGrate
Firing system details WtE Monitor+Available with WtE Monitor+
Hourly capacity WtE Monitor+Available with WtE Monitor+
Feedstockresidual municipal solid waste, commercial and industrial waste, waste wood, MBT residues, RDF, plastics
Steam parameters WtE Monitor+Available with WtE Monitor+
Electrical output WtE Monitor+Available with WtE Monitor+
District heat output WtE Monitor+Available with WtE Monitor+
District heat use WtE Monitor+Available with WtE Monitor+
Flue gas cleaning WtE Monitor+Available with WtE Monitor+
Technology suppliers WtE Monitor+Available with WtE Monitor+
Designer / EPC contractor WtE Monitor+Available with WtE Monitor+
Ownership WtE Monitor+Available with WtE Monitor+
Commissioning by line2009 (first planning permission); 2013 (revised permission 13/0725/WA); 2020 (planning 19/1172 approved, permit variation to conventional combustion); December 2023 (financial close); November 2024 (start of construction by Kanadevia Inova after ten months of site remediation; permit variation V004 to one line); 2026 (boiler, grate and turbine installed); late 2027 (planned start of operation)
Projects in progressUnder construction; pressure tests from early 2026; steam turbine, boiler drum and grate components installed by July 2026; about 500 workers on site; recruitment of ca. 45–60 permanent staff started 2026; district heat network for Walsall planned (CHP-ready design, up to 20 MWth); operation expected late 2027
AddressWalsall Energy Recovery Facility, Fryers Road, Bloxwich, Walsall WS3 2XJ

Location

Nearby plants

Sources

8 sources for this profile. The list is part of WtE Monitor+

AI search

Ask WtE Monitor

Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.

Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy

3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+