- Permitted capacity
- 242 kt/a
- Commissioned
- 2011
- Energy recovery
- Electricity
The Newhaven Energy Recovery Facility on North Quay Road beside the River Ouse is operated by Veolia for East Sussex County Council and Brighton & Hove City Council and treats around 210,000 tonnes of residual household waste a year, roughly half of the area’s household waste, much of it residual material from Veolia’s Hollingdean MRF in Brighton.
Construction began in April 2008 and the plant, which cost about £175 million and was partly sunk 20 m into the ground in a floating caisson to reduce its height, has been operational since 2011. Steam of 88 t/h drives a turbine generator of about 19 MW, exporting around 16 MW to the grid, enough for some 25,000 homes. Flue gases are discharged through two 65 m chimneys.
| Firing system | Grate |
|---|---|
| Firing system details | WtE Monitor+Available with WtE Monitor+ |
| Feedstock | residual household waste from East Sussex and Brighton & Hove (incl. residues from Hollingdean MRF) |
| Electrical output | WtE Monitor+Available with WtE Monitor+ |
| Flue gas cleaning | WtE Monitor+Available with WtE Monitor+ |
| Ownership | WtE Monitor+Available with WtE Monitor+ |
| Commissioning by line | 2011 (construction April 2008 to late 2011; operational from June 2011 / full operation 2012) |
| Address | North Quay Road, Newhaven BN9 0AB |
Location
Open in Google Maps · 50.8016, 0.0493
Nearby plants
- Maidstone63 km
- Sutton (Beddington)66 km
- Tilbury75 km
- Shepperton76 km
Sources
5 sources for this profile. The list is part of WtE Monitor+
Ask WtE Monitor
Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.
Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy
3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+
