NLWA Agrees Revised £1.25bn Contract to Complete Edmonton ERF

North London’s waste authority has struck a new deal to finish its Edmonton incinerator. Why did Members decide that pulling the plug was no longer an option?

Construction site of the new Energy Recovery Facility at Edmonton EcoPark
Construction site of the new Energy Recovery Facility at Edmonton Ecopark (Source: NLWA)

Key Takeaways

  • NLWA agreed a revised £1.25bn contract on 12 November 2026 to complete the Edmonton ERF by December 2029.
  • Contractor Acciona takes on more risk; £700m has already been spent.
  • Cancellation would have cost the boroughs an extra £100m a year by 2030/31.
  • Inflation and labour shortages have delayed construction since 2022.
  • Members requested further cost analysis and more robust monitoring.

North London Waste Authority (NLWA) agreed revised terms on 12 November 2026 to complete the publicly owned Energy Recovery Facility (ERF) at Edmonton EcoPark. The new agreement sets a revised contract price of £1.25bn and a completion date of December 2029. Contractor Acciona takes on more risk that was previously held by NLWA.

The ERF is at an advanced stage, and £700m has already been spent. NLWA is a public body governed by 14 elected representatives from seven north London boroughs. All decisions are made by NLWA Members.

Cancellation Would Have Cost Boroughs £100m a Year

According to NLWA, the boroughs would have faced an additional £100m a year by 2030/31 if the ERF had been cancelled. This sum would have included repayments on existing loans and payments to private operators to incinerate or landfill north London’s waste elsewhere. Around 30,000 additional lorry journeys a year would have been needed to transport the waste to those sites.

“NLWA Members have closely examined the incinerator project. It’s now over 60% complete and alternatives to deal with the rubbish of two million residents would be about 60% a year more expensive for decades to come,” said Cllr Jacob Cable, Chair of NLWA. At this late stage of construction and taking all the facts into consideration, Members had concluded that it was in the public interest to finish the facility and agree the new terms. “Cancelling the project at this stage would impose significantly greater costs on the boroughs.”

Cost per Resident of About £1.50 a Week

Once the facility is finished, the cost per north London resident will be about £1.50 per week. This covers the collection and disposal of rubbish and recycling as well as access to eight Reuse and Recycling Centres.

The amount also funds other initiatives. These include an education programme and at least £250,000 a year in grants for community-led projects to reduce waste, increase reuse and recycling and encourage innovation.

Inflation and Labour Shortages Delayed Construction

Construction of the ERF began in 2022. Since then, the project has been affected by inflation, higher interest rates, increased material costs and labour shortages. A lack of skilled subcontractors for the mechanical and electrical works, including systems such as boilers and flue-gas treatment equipment, was a significant issue. The resulting delays led to disputes and to rising associated costs for Acciona.

According to NLWA, the authority and Acciona have collaborated more closely since earlier this year to resolve issues. Productivity has recently improved: more than 400 skilled workers are on site every day, compared with 200 at the beginning of the year. The turbine has been installed.

Contractor Accountable for Delivery and Commissioning

“Members have ensured that the new agreement is robust and binding, with the contractor fully accountable for the delivery and commissioning of the facility,” said Cable. Independent expert advisers had carried out in-depth reviews, and Acciona’s performance had been audited. This had led to increased governance and oversight.

Cable stressed that the facility will be publicly owned and that income from energy generation will continue to help reduce costs for council taxpayers. “There will never be a situation in north London where our boroughs are locked into a contract with a private provider which forces us to supply waste for burning.”

Same Flue-Gas Technology as in Copenhagen

According to Cable, the new facility will improve on the current incinerator, particularly in terms of air quality. The technology installed to capture and control pollutants is the same as that used in a facility close to the centre of Copenhagen, which has a ski slope on its roof.

Cable said local councils bear the statutory responsibility to dispose of large volumes of rubbish, driven by short-lived products whose manufacture and distribution harm the planet. Following the decision to complete the ERF, NLWA Members will push for systemic change to reduce waste as far as possible, including far less plastic being incinerated. “We call on this Government to act and urgently ban more unnecessary, tricky-to-recycle plastic.”

Cable has also written to the Government to request funding support for emerging green technologies. NLWA wants circular economic activities scaled to an industrial level. This should be accompanied by measures to develop end markets so that the materials produced can be used sustainably and at scale.

Members Request Further Cost Analysis

During the meeting, NLWA Members agreed a number of follow-up actions and requested further information from officers. These include:

  • a more granular breakdown of the assumptions underpinning future costs to boroughs
  • further analysis of how to control borough levies
  • confirmation of the approved construction and commissioning programme
  • more robust monitoring and reporting

Read More

AI search

Ask WtE Monitor

Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.

Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy

3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+

Free newsletter

Waste-to-energy news, straight to your inbox.

Projects, policy and plant data from across Europe. Get every story as it is published, or switch to a daily or weekly digest.

Free. Confirm by email. Change the frequency or unsubscribe at any time.

Leave a Reply