ZMS
-

Two Furnace Lines Gone: Schwandorf’s 2025 in Numbers
In December 2025, incineration lines 2 and 3 at the Schwandorf waste-to-energy plant were permanently decommissioned as part of the ‘Triphönix’ refurbishment project. Previously, all four lines had…
-

Thomas Ebeling re-elected as ZMS chairman
Thomas Ebeling has been re-elected as chairman of ZMS for a six-year term until 2032, overseeing a significant project called Triphönix. This €430 million initiative aims to modernise…
-

Schwandorf WtE Plant Halts Commercial Waste Acceptance
The Schwandorf waste-to-energy plant has temporarily halted commercial and construction waste intake from 11 to 13 March 2026 due to a furnace failure during upgrades, leaving only one…
-

End of an Era: Schwandorf’s Furnace Line Shutdown
The decommissioning of furnace line 3 at the Schwandorf plant marks the start of ‘triphönix’, a significant investment aimed at enhancing sustainable energy in the region. Operational since…