- Permitted capacity
- 685 kt/a
- Incineration lines
- 2
- Commissioned
- 2027
- Energy recovery
- Electricity
The Lostock Sustainable Energy Plant (LSEP) is a two-line Energy-from-Waste plant being built on the former coal-fired power station site at Lostock Works near Northwich, Cheshire, adjacent to the Tata Chemicals Europe soda ash works.
The GBP 480 million project is owned by a joint venture of Copenhagen Infrastructure Partners (60%) and FCC Environment (40%), which will operate it, and is permitted for 685,000 tonnes of residual municipal, commercial and industrial waste and SRF a year with a design gross output of about 77 MWe.
Originally consented to Tata Chemicals Europe in 2012 and due to open in 2023, the plant was delayed when EPC contractor CNIM collapsed in January 2022. Black & Veatch took over as EPCM contractor with Babcock & Wilcox supplying the power train, and hot commissioning is now planned for late 2026 with full operation expected in the first half of 2027.
| Firing system | Grate |
|---|---|
| Firing system details | WtE Monitor+Available with WtE Monitor+ |
| Thermal input | 240 MWth |
| Hourly capacity | WtE Monitor+Available with WtE Monitor+ |
| Waste calorific value | WtE Monitor+Available with WtE Monitor+ |
| Feedstock | residual municipal solid waste, commercial and industrial waste, solid recovered fuel (SRF) |
| Steam parameters | WtE Monitor+Available with WtE Monitor+ |
| Electrical output | WtE Monitor+Available with WtE Monitor+ |
| Operating hours | 8,000 h/a |
| Flue gas cleaning | WtE Monitor+Available with WtE Monitor+ |
| Technology suppliers | WtE Monitor+Available with WtE Monitor+ |
| Designer / EPC contractor | WtE Monitor+Available with WtE Monitor+ |
| Ownership | WtE Monitor+Available with WtE Monitor+ |
| Commissioning by line | planned: hot commissioning (first waste) Q4 2026, full operation first half of 2027 (Lines 1-2) |
| Projects in progress | Environmental permit varied June 2024 (EPR/WP3934AK/V004) to raise throughput from 600,000 to 685,000 t/a with annual throughput interlock and reduced NOx limit; Secretary of State refused a Section 36 variation to 728,000 t/a in December 2022; LSEP announced in June 2026 a new S36C application for 728,000 t/a (pre-submission consultation to 21 July 2026, submission to DESNZ expected late 2026); plant is 'CHP Ready' but has no heat off-takers yet |
| Address | Lostock Works, Griffiths Road, Lostock Gralam, Northwich, Cheshire CW9 7NU |
Location
Open in Google Maps · 53.2623, -2.4770
Nearby plants
- Runcorn20 km
- Ince24 km
- Stoke-on-Trent36 km
- Deeside37 km
Sources
18 sources for this profile. The list is part of WtE Monitor+
Ask WtE Monitor
Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.
Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy
3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+