Waste-to-energy plant ·

Ince

Protos Energy Recovery Facility
Source: blackboxguild – stock.adobe.com

Operator: Encyclis · Under construction · Data verified 22.10.2026

Permitted capacity
500 kt/a
Incineration lines
2
Commissioned
2026
Energy recovery
Electricity

Protos Energy Recovery Facility is being commissioned by Encyclis on Peel’s Protos energy and resource hub at Ince near Ellesmere Port, Cheshire.

The two-line moving grate plant, built by a consortium of Standardkessel Baumgarte and METLEN (Mytilineos) after financial close in December 2020 for the Biffa-Covanta-Green Investment Group joint venture, is permitted for 500,000 tonnes of residual waste per year and up to 49.9 MW of electricity.

First fire on waste was achieved in August 2026. Encyclis bought out Biffa’s 25 per cent stake in 2025 and now owns the plant outright, with Biffa remaining the anchor waste supplier. On adjoining land Kanadevia Inova is building the UK’s first full-scale carbon capture plant for energy from waste, which is to capture around 370,000 tonnes of CO2 a year from 2029 for storage in Liverpool Bay via the HyNet North West cluster.

Technical data
Firing systemGrate
Firing system details WtE Monitor+Available with WtE Monitor+
Thermal input148 MWth
Hourly capacity WtE Monitor+Available with WtE Monitor+
Waste calorific value WtE Monitor+Available with WtE Monitor+
Feedstockresidual household waste, commercial and industrial waste, refuse-derived fuel (Biffa anchor supplier)
Accepted waste types (EWC codes) WtE Monitor+Available with WtE Monitor+
Steam parameters WtE Monitor+Available with WtE Monitor+
Electrical output WtE Monitor+Available with WtE Monitor+
Flue gas cleaning WtE Monitor+Available with WtE Monitor+
Technology suppliers WtE Monitor+Available with WtE Monitor+
Designer / EPC contractor WtE Monitor+Available with WtE Monitor+
Ownership WtE Monitor+Available with WtE Monitor+
Commissioning by line2026 (Lines 1-2; construction from 2020/21, hot commissioning from February 2026, first fire on waste August 2026; commercial operation still outstanding as of October 2026)
Modernisation / expansion WtE Monitor+Available with WtE Monitor+
Projects in progressCarbon capture: Protos CCS plant under construction on an adjoining 4.4-acre site (EPC Kanadevia Inova; piling from mid-2026), post-combustion amine (MEA) capture of about 370,000 t CO2 per year (permit: up to 412,500 t/a, 95 per cent capture, two capture lines, 105 m stack, 56.4 MWth steam extraction, net generation falling to 36.1 MWe); selected in the Track-1 HyNet North West cluster, public-private funding agreement with DESNZ (financial close October 2025), completion due 2029 with CO2 piped to Liverpool Bay for subsea storage. Permit variation V009 for the capture plant issued December 2024.
AddressProtos Energy Recovery Facility, Generation Road, Ince, Chester CH2 4JF

Coverage of this plant

Location

Nearby plants

Sources

11 sources for this profile. The list is part of WtE Monitor+

AI search

Ask WtE Monitor

Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.

Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy

3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+