- Permitted capacity
- 85 kt/a
- Incineration lines
- 1
- Commissioned
- 2028
- Energy recovery
- CHP
Paprec Energies Binn, a joint venture of the French waste group Paprec and the Perthshire family company Binn Group, is building a single-line energy recovery facility at Binn Eco Park near Glenfarg in Perth and Kinross, on the site of Binn Group’s existing waste treatment and recycling centre.
The EUR 120 million plant is designed for up to 85,000 tonnes of residual waste per year on a two-lane Martin reverse-acting grate (11.5 t/h) and is to supply up to 8 MW of electricity and 17 MW of heat to the eco park’s private energy network and local businesses.
Full construction started in May 2024 with operation planned for early 2026, but work was halted in autumn 2024 because of a delayed grid connection. By 2026 Zero Waste Scotland listed the project as paused with no commissioning plan and a notional target of 2028.
Perth and Kinross Council, which had awarded Paprec Energies Binn a ten-year, GBP 50 million residual waste contract in 2023, agreed in December 2025 to terminate that contract by mutual consent and to send its waste to Cireco in Fife instead.
| Firing system | Grate |
|---|---|
| Firing system details | WtE Monitor+Available with WtE Monitor+ |
| Hourly capacity | WtE Monitor+Available with WtE Monitor+ |
| Feedstock | residual municipal solid waste (Perth and Kinross) and commercial and industrial residual waste |
| Electrical output | WtE Monitor+Available with WtE Monitor+ |
| District heat output | WtE Monitor+Available with WtE Monitor+ |
| District heat use | WtE Monitor+Available with WtE Monitor+ |
| Technology suppliers | WtE Monitor+Available with WtE Monitor+ |
| Designer / EPC contractor | WtE Monitor+Available with WtE Monitor+ |
| Ownership | WtE Monitor+Available with WtE Monitor+ |
| Commissioning by line | 2007/2011 (earlier planning consents for SITA mass-burn and gasification plants on the site); 2020 (planning 20/01242/FLM, capacity increase); November 2023 (Martin grate order); May 2024 (start of full construction, operation planned early 2026); October 2024 (construction halted over grid connection delay); 2028 (notional target per Zero Waste Scotland, no commissioning plan) |
| Projects in progress | Construction paused since autumn 2024 (grid connection delay); SEPA PPC permit application was described as imminent in April 2024; Zero Waste Scotland (August 2026) lists the facility as planned/paused with a targeted commissioning date of 2028 and no official commissioning plan; Perth and Kinross Council terminated its residual waste contract in December 2025 and awarded an 18-month emergency contract to Cireco |
| Address | Binn Eco Park, Binn Farm, Glenfarg, Perth PH2 9PX |
Location
Open in Google Maps · 56.3052, -3.3403
Nearby plants
- Westfield, Fife16 km
- Dundee34 km
- Grangemouth41 km
- Millerhill45 km
Sources
10 sources for this profile. The list is part of WtE Monitor+
Ask WtE Monitor
Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.
Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy
3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+
