Waste-to-energy plant ·

Glasgow (Polmadie)

Ulm’s WtE Plant Charts Its Next Move
A long cloud of white smoke escaping from a metallic chimney against a deep blue sky.

Operator: Viridor · Operating · Data verified 22.10.2026

Permitted capacity
197.1 kt/a
Incineration lines
3
Commissioned
2019
Energy recovery
Electricity

The Glasgow Recycling and Renewable Energy Centre (GRREC) at 425 Polmadie Road on the south side of Glasgow is operated by Viridor (Viridor (Glasgow) Ltd) under a 25-year contract with Glasgow City Council and combines a materials recycling facility, an anaerobic digestion plant with biogas engines and a three-line thermal treatment plant for the residual fraction.

The thermal lines were originally designed as gasification units but are permitted and operated by SEPA as incineration lines. The plant has been operational since 2019.

In March 2026 SEPA raised the permitted throughput from 154,000 to 197,100 tonnes a year (7.5 t/h per line). No heat is currently exported, although Viridor says the plant produces enough heat for around 8,000 homes.

Technical data
Firing systemGasification
Firing system details WtE Monitor+Available with WtE Monitor+
Hourly capacity WtE Monitor+Available with WtE Monitor+
Waste calorific value WtE Monitor+Available with WtE Monitor+
Feedstockresidual municipal solid waste from Glasgow City Council (green bin) after mechanical pre-treatment, plus organic waste to anaerobic digestion
Operating hours8,760 h/a
Flue gas cleaning WtE Monitor+Available with WtE Monitor+
Ownership WtE Monitor+Available with WtE Monitor+
Commissioning by line2019 (three thermal lines; Viridor: operational since 2019)
Projects in progressSEPA permit variation VAR03 (25 March 2026): throughput increased from 154,000 to 197,100 t/a (6.5 to 7.5 t/h per line), with performance and residence-time tests, updated dispersion modelling and NOx/PM improvement measures for the AD biogas engines by 30 September 2026; heat export of c. 7 MWth identified as necessary to meet long-term energy efficiency targets
AddressGlasgow Recycling and Renewable Energy Centre, 425 Polmadie Road, Glasgow G42 0PJ

Location

Nearby plants

Sources

6 sources for this profile. The list is part of WtE Monitor+

AI search

Ask WtE Monitor

Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.

Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy

3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+