Headquarters: Bassum · Public / municipal · hkw-blumenthal.de · Figures for 2024 · Data verified 17.10.2026 ·

WtE plants
1
WtE capacity
65 kt/a

HKW Blumenthal GmbH operates a refuse-derived-fuel combined heat and power plant on the former Bremer Wollkämmerei site in Bremen-Blumenthal. The 65,000 t/a plant is wholly owned by AWG Bassum, the waste company of Landkreis Diepholz, and burns the high-calorific fraction from AWG’s residual waste treatment plant in Bassum.

After a EUR 13.5 million conversion completed in 2025, the plant now feeds the first district heating network in Bremen-Nord, which enercity Contracting is building out until 2035. The Klinikum Bremen-Nord has been supplied since June 2026.

Key Takeaways

  • Founded in 2004 as a joint venture of AWG Bassum and Bremer Woll-Kämmerei AG (BWK) to convert BWK’s coal-fired works power station to refuse-derived fuel; the company has been wholly owned by AWG since 2009, which in turn belongs entirely to Landkreis Diepholz.
  • One grate-fired line with 31 MW thermal input and a permit for 65,000 t/a of RDF, commissioned in June 2005, produces electricity for the public grid and heat for the Kämmerei-Quartier in Bremen-Blumenthal.
  • Fuel comes from AWG’s own RABA mechanical-biological treatment plant in Bassum, which makes the Bremen plant part of the public waste disposal system of the district of Diepholz under the district’s waste bylaw.
  • A long-term heat partnership with Enercity Contracting, signed on 9 February 2023 and firmed up with a heat supply contract on 29 June 2023, triggered a one-year conversion of the plant with a new turbine, 15 MW of heat extraction and backup boilers.
  • The Bremen-Nord district heating network has been under construction since early 2025; the Klinikum Bremen-Nord was connected on 22 June 2026, three Blumenthal schools follow in the second half of 2026 and further phases start in early 2027.
Key data
Founded2004
Figures for2024
Ownership WtE Monitor+Available with WtE Monitor+
Other activitiesRDF-fired combined heat and power plant (65,000 t/a); electricity to the public grid; district heat to the Kämmerei-Quartier and the new Bremen-Nord heat network; 200 kWp photovoltaic system on site
Projects in progress WtE Monitor+Available with WtE Monitor+

Plants operated by HKW Blumenthal

1 plant in the WtE Monitor database, 65 kt/a in total.

WtE Monitor+

Continue with WtE Monitor+

This content is part of WtE Monitor+: every plant, company and country profile, in-depth analyses and Ask AI.

Sources

25 sources for this profile. The list is part of WtE Monitor+

AI search

Ask WtE Monitor

Answers come only from WtE Monitor articles and plant data, with sources. Ask in any language.

Your question is processed by Anthropic to generate the answer. Please do not enter personal data. Privacy policy

3 questions a month with a free subscription, unlimited with WtE Monitor+. Subscribe free · Get WtE Monitor+